- PFE: For Perth , Sydney, Adelaide and Torquay have been manufactured & tested
- Cable: 38% of the cable has been completed, with 2042 km out of 5265 km manufactured
- Repeaters: 71% completion, with 43 out of 60 repeaters manufactured and tested
- Branching Units: No progress yet on the manufacturing of Branching Units
We also conducted a recent meeting with System Suppliers to address any outstanding issues following the marine survey. Key focus areas included:
- Finalising the completion of manufacturing processes
- Preparing for system assembly and testing phases
- Ensuring readiness of the land route and landing station infrastructure
- Planning the load and lay program to align with the project’s timeline