The Bernacchi-1 project at Bellbuoy Beach spans planning, design approvals, installation and commissioning for the delivery of the project for Tasmania.
These phases and critical milestones include:
Phase 1: Planning
June - Sept 2026
ยท Initial route selection
ยท Agency consultation project briefings
ยท Planning assessment and desktop studies completed
Phase 2: Final survey and design
Oct - Nov 2026
ยท Marine route survey activities undertaken to determine final cable route
ยท Site investigations/ground conditions investigations at HDD location & cable shelter
ยท Survey approvals
Phase 3: Cable installation approvals
Nov 2026 - Jan 2027
ยท George Town council development consent โ Planning consent
ยท Crown lands consent
ยท NRE and parks consent
ยท Cultural heritage consent
Phase 4: Installation
Nov 2026 - Feb 2027
ยท Beach manhole and HDD out to sea construction
ยท HDD and beach manhole installation
ยท Front haul street conduit works
ยท Cable landing shelter construction
Mar 2027
ยท Subsea cable installation works
ยท Street cable hauling works
Phase 5: Network commissioning
Feb - Mar 2027
ยท Equipment install and testing of system