The Bernacchi-1 project in Bellbuoy Beach has a number of phases both in the planning and design approvals phase and into the installation and commissioning phases for the delivery of the project for Tasmania.
These phases and critical milestones are highlighted below:
Phase 1: Planning
· June 2026 - Sept 2026
· Initial route selection
· Agency consultation project briefings
· Planning assessment and desktop studies completed
Phase 2: Final survey and design
· Oct 2026 - Nov 2026
· Marine route survey activities undertaken to determine final cable route
· Site investigations/ground conditions investigations at HDD location & cable shelter
· Survey approvals
Phase 3: Cable installation approvals
· Nov 2026 - Jan 2027
· George Town council development consent – Planning consent
· Crown lands consent
· NRE and parks consent
· Cultural heritage consent
Phase 4: Installation
· Nov 2026 - Feb 2027
· Beach manhole and HDD out to SEA construction
· HDD and beach manhole installation
· Front haul street conduit works
· Cable landing shelter construction
· Mar 2027
· Subsea cable installation works
· Street cable hauling works
Phase 5: Network commissioning
· Feb - Mar 2027
· Equipment install and testing of system